4.5 How to Organize the Project Folder
Introduction
The PCS 7 Wizard has created and named Unit(1) of the "fast_Prj" project. In the following,
you will rename these hierarchy folders:
Folder "Plant(1)" will become "PLANT"
"Unit(1)" will become "UNIT_A"
This will make the plant structure clearer.
Objects created by the PCS 7 Wizard that are not required can be deleted
Requirements
You have completed the session in the PCS 7 Wizard "New Project".
SIMATIC Manager is open and the "fast_MP" project and all open hierarchy folders are
displayed in the Plant view.
Note
You can configure the different views in SIMATIC Manager by selecting View > and then, for
example, Plant View.
Procedure
Step Action
1 Open the shortcut menu of the "Process cell(1)" folder in the left pane of the Plant view and
select Rename.
2 Enter the name "PLANT" and press Enter.
3 Open the shortcut menu of the "Unit(1)" folder in the left pane of the Plant view and select
Rename.
4 Enter the name "UNIT_A" and press Enter.
5 Click the "Function(1)" folder below the "UNIT_A" folder.
6 Open the shortcut menu of the "CFC(1)" object in the right-hand window and select Delete.
The "Delete" dialog box opens.
7 Click "Yes".
Configuring the process tags and the sequential control
4.5 How to Organize the Project Folder
Getting Started (V8.1 with APL)
40 Getting Started, 07/2014, A5E32713210-AA

Table of Contents

Other manuals for Siemens SIMATIC PCS 7

Related product manuals