Preparing the process picture for automatic generation
5
5.1 How to Prepare the Plant Display for Automatic Generation.
Introduction
To prepare for automatic process picture generation, take the steps described below.
Requirements
You have completed the session in the PCS 7 Wizard "New Project".
SIMATIC Manager is open and the "fast_MP" project and all open hierarchy folders are
displayed in the Plant view.
Procedure
Step Action
1 Select the "UNIT_A" folder in the left-hand window of the Plant view.
2 Open the shortcut menu of the "Picture(3)" object in the right window and then select the
Object Properties ... menu command.
3 Select the "Block icons" tab.
4 Select the "Derive block icons from the plant hierarchy" check box and click "OK".
5 Open the shortcut menu of the "UNIT_A" folder and select Plant Hierarchy > Customize.
The "Plant Hierarchy - Settings" dialog box opens.
6 Select the radio button in the "OS area" column for the second level in the "Level Settings"
group.
7 Select the "Derive picture hierarchy from the plant hierarchy" check box.
8 Click "OK".