Installation
3.2 System Installation
Distributed converter for SIMOGEAR geared motors
40 Getting Started, 04/2018, FW V4.7 SP10, A5E36100338B AG
Connecting the mains cables (HANQ variant)
Ensure that the cable clamp has been removed.
Connect the HANQ L1, L2 and L3 connections to the L1, L2
and L3 connections on the mains connector.
When the connections are completed, replace the cable
clamp over the cables (ensuring that the cable clamp is the
correct way round).
Tightening torque of the mains terminals are a maximum of 0.8
Nm.
Connecting the power-through cables (HANQ variant)
To allow the power provided to one system to supply the po
w-
er to another system in a daisy
-
chain, the input power is routed
directly from the mains input HANQ co
nnector to the mains
output connector in the same Terminal Housing.
Connect the Earth connection from the input HANQ
connector to the output HANQ connector.
Connect the L1 connection from the input HANQ connector
to the output HANQ connector.
Connect the L2 connection from the input HANQ connector
to the output HANQ connector.
Connect the L3 connection from the input HANQ connector
to the output HANQ connector.
-through cables are provided with the Terminal
Housing and are the correct size an
d dimensions to allow the
power-through connections to be made easily.