14 Maintenance
14.1 Preventive maintenance
Tasks to be carried out weekly:
- check all panel indications and press "Led test"
Tasks to be carried out annually:
- check automatic activation
- check manual activation
- check released condition by activation of the discharged contact
- check emergency hold/abort devices
- check mechanical blocking device
- check loss of agent indication
- check batteries (visual)
Tasks to carry out every 2 years:
- clean the control panel with soft soap. Do not use any aggressive solvent or
containing abrasive material
- check labels legibility and exactitude
- check each operating key
- check operating access levels
Tasks to carry out every 4 years:
- check all fire detectors
- check all detection circuit shorts and breaks
- check earthing connection
- replace batteries
- replace pyrotechnical actuators (is used)

Table of Contents

Other manuals for Siemens XC1005-A

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens XC1005-A and is the answer not in the manual?

Siemens XC1005-A Specifications

General IconGeneral
BrandSiemens
ModelXC1005-A
CategoryControl Unit
LanguageEnglish

Related product manuals