Instructions, use and maintenance manual Pag. 21/49
SAU 160-200
11.2. Description of the adjustment and commissioning operations
11.2.1. Installation
The machine must be positioned vertically on a smooth surface and able to support the weight (floor
with resistance above 20 kgcm
2
). The walls and the floor must be in good condition and easy to clean.
If there is a risk of overturning, anchor the machine to the floor using 4 wedges or bolts with tensile
strength greater than 300 kg (M8) with the specific anchors that can be supplied on request.
ATTENTION: Before operating the mixer machine, make sure that the feet are aligned
so that the machine is not unbalanced.
ATTENTION: Before operating the mixer machine, make sure that the feet are aligned
so that the machine is not unbalanced.