EasyManua.ls Logo

SMA SUNNY BOY 2000HF - Restarting the Self-Test

SMA SUNNY BOY 2000HF
96 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
SMA Solar Technology AG Commissioning
Installation Guide SB20_25_30HF-IEN102911 59
7.3.4 Restarting the Self-Test
In order to restart the self-test, proceed as follows:
1. Disconnect the line circuit breaker and secure against re-connection.
2. If a multi-function relay is connected, switch off the multi-function relay power supply.
3. Disconnect the Electronic Solar Switch from the inverter for 5 minutes and then connect it again.
4. Switch on the line circuit breaker again.
The inverter is now in the initialization phase and you can restart the self-test, as described in
section 7.3.1”Starting the Self-Test” (page54) from point 3.

Table of Contents

Other manuals for SMA SUNNY BOY 2000HF

Related product manuals