5. Commissioning
5.1. Double Check
Please double check the following items before running:
Battery module and the base should be completely fixed.
Each BAT+/BAT- line is firmly connected, the polarity is correct, and
the voltage is in line with the accessible range.
The DC switch of the BDU(or ESI Series Inverter)is OFF, and the
black start indicator is OFF.
Ensure that the communication cable is firmly connected to the
terminal resistor.
Install sealing plugs on unused terminals or interfaces.
Cable is arranged reasonably, and the cable is tidy and without
damage.
5.2. Electrify for the First Time(Important)
1) Set the DC switch of the BDU(or ESI Series Inverter)to ON.
2) Press the black start switch on the BDU(or ESI Series Inverter)to
power on the battery for the first time. Observe the LED indicator on
the BDU(or ESI Series Inverter)to check the running status.
5.3. Software Update and Battery monitoring
The product can be upgraded through the software of SOFARSOLAR
ESI Series Inverter to maximize the performance of the product and avoid
the abnormal operation of the product caused by software bugs.
Before upgrading the software, check that the communication cables of