Site Planning Checklist
1-6 Stratus ftServer 29x0, 49x0, and 69x0 Systems: Site Planning and Installation Guide (R786)
Have you created a sketch of how you plan to arrange the system at the installation
site? Consider the available cable lengths, the placement of external devices, and
the location of network and voice communication connections.
On the sketch, show the following:
Location of the system and its external components
Power cords, and telephone and interface cables
Locations of AC power receptacles, phone jacks, Ethernet jacks, switches, and
hubs
NOTE
Make sure that all cords and cables are long enough to
reach between their respective components and
connectors. Route all cables out of the way of foot traffic.
Working with Other Groups
Have you provided your facilities group and contractors with the sketch of how you
plan to arrange the system and copies of the following?
“AC Power and HVAC Service Requirements” on page 2-2
“Redundant Power Sources” on page 2-1
Tables 2-1, 2-2, and 2-3, worksheets for determining AC power requirements
Tables 2-5 and 2-6 (if you are using PDUs) or Tables 2-7 and 2-8 (if you are not
using PDUs), worksheets for determining the number of external power outlets
required
Appendix B, “Electrical Circuit and Wiring Information”
Any notes you have about site planning
Have you reviewed and discussed the requirements with the facilities personnel
and contractors to ensure that all site modifications are understood and
implemented?
If you have any questions about the number and types of components, contact your
Stratus account representative or distributor.