figure 5-1 Hoisting the MV Station
5.2.2 Hoisting
During the whole hoisting process, please observe the following rules:
Hoist the MV Station in a vertical manner. Do not drag or drop the MV Station on any
surface.
Keep the container stable and horizontal during hoisting, and ensure that the diagonal
gradient of the container is within 5 degrees.
When the MV Station has been hoisted for about 300mm away from the ground, stop to
check if all the connections are still firm. After confirmation, continue hoisting the MV
Station.
Lift and land the container slowly to prevent shock to the internal devices.
When transported to the final location, the MV Station should be put down slowly and
steadily.
The final location should be firm, level, and well-drained. The MV Station is supported by
four bottom fittings on the ground.
Remove the ropes after ensuring that the container is placed evenly on the container
bases.
Secure the container hoisted before hoisting another one.
The MV Station should be hoisted by four top corner fittings as shown in the following figure.
5 Mechanical Installation System Manual