Trane GAF2A0A36M31EC - Refrigerant Line Brazing; Brazing Refrigerant Lines

Trane GAF2A0A36M31EC
32 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
18
1.5” MIN
STEP 1 - Remove Heater, Coil, and Line Set panels.
Section 11. Refrigerant Line Brazing
11.1 Braze The Refrigerant Lines
STEP 6 - Connect, but do not braze, field line set to
indoor coil.
Allow a minimum of 1.5 inches of refrigerant line set
before using an elbow coupling.
Important: Service access to the auxiliary heater
must remain unobstructed.
(See Section 2.2 Panel Removal)
Important: Do NOT unseal coil refrigerant connection
stubs until ready to make connections.
Important: Heat Sensitive Bulb.
The TXV sensing bulb must be removed or a wet rag
must be wrapped around the suction line between the
Bulb and the braze joint to protect the Bulb from failure
due to overheating.
Caution: This coil is pressurized with 8-12 psig of dry
air. Do not stand directly in front of the coil connections
when removing sealing plugs.
Step 2 - Remove the sealing plug from the indoor coil
liquid connection.
NOTE: A small amount of pressure should be re-
leased.
Heater
Panel
Line Set
Panel
Coil
Panel
1
2
3