Vertiv | Liebert LVC | User Manual 7
Installation
Figure 1-3 Crane Lifting
• Before lifting., please to ensue the liting capacity of the equipment is greater than the weight of the
unit, refer the weight of the unit in the Technical Specication as per model number.
• There are two holes in each of the front and back bottom beams for xed lifting ropes, and the lifting
ropes need to go through the beam opening. The user can also use a cord or other method to x
lifting ropes here, to prevent the rope sliding during the lifting process.
• It is prohibited to install lifting bolts in other parts of the unit frame bottom. When installing the lifting
equipment, it is necessary to shelter the surface and ns of the unit, to avoid scratching.
• The warning board should be utilized in work area, it is prohibited to non-relevant personnel to enter.
• The lifting of units is a dangerous operation, which must be a responsibility of the skilled technicians
and avoid the non-professional personnel to operate.
• If high wind speed is identied on site, please stop lifting work, until it is back to normal.
1.1.2. Unpacking
Remove the frame package and foam of the condenser without removing the protection cardboard of the ns.
The protection cardboard of ns and the cushion pad of U tube located at the end of the condenser should be
removed after the condenser is in its installation position.