Vertiv I VRC Self-Contained System I User Manual
2.1 Fittings
The hardware used for fittings are shown in Figure 2-1.
Figure 2-1 Fittings
The fitting nuts and their usage are shown in Table 2-1.
Table 2-1 Fitting utilities
2.2 Self-Prepared Material
The circuit breakers must be prepared at the customer site or are to be obtained by the customer; the
specifications for the same are given in Table 2-2.
Table 2-2 Self-prepared materials
Please refer to FLA of Unit
2.3 Transportation and Movement
The VRC1 need to be moved to the vicinity of the installation site. The cooling unit with heavy components,
needs to be transported using equipment such as a hand pallet truck or electric forklift. Table 2-3 and
Figure 2-2 show the dimensions of the unit with packaging.
Figure 2-2 Package dimensions
Used with M6 pan-head screws for tightening pillars
Used to fasten the L-shape rails
Used to fasten the transition part
Used to install the VRC 10X unit
Used together with the M5 pan-head screw