43
Remove the transport brackets and store
with the system for servicing work or
subsequent transport operations.
Filling the siphon with water
!
Please note
During commissioning, flue gas
may escape from the condensate
drain.
Fill the siphon with water before
commissioning.
1. Take the siphon out of the retainer
and remove inlet pipe. If necessary,
remove the drain pipe and power
cable.
2. Pour water into the inlet connection.
Installation sequence
Removing the transport brackets
(cont.)
5618 294 GB
Installation