78
If necessary, change the length by turn-
ing the upper nuts on the four retaining
rods.
Checking the diaphragm expansion vessel and system pressure
Check the diaphragm expansion vessel
pre-charge pressure (on site) and top up
if required.
Checking for firm terminal connections
1. Check all cables for correct seating. 2. Check cables on the Stirling engine
for breakages and abrasion points.
Replace damaged cables.
Commissioning, inspection, maintenance
Further details regarding the individual steps
(cont.)
5618 294 GB