4.10 Pre-Starting Checks
Prerequisites
Machine properly positioned
Checks
Before starting the machine, check the following items:
Fuel System
Fuel sight gauge valve
(a)
f Check that the fuel sight
gauge valve is open.
Fuel sight gauge
(b)
f Check that there is fuel in the
tank.
Heat Transfer Fluid (HTF) System
Suction valve
(#2)
f Check that suction valve (#2)
is opened.
HTF fill valve
(#3)
f Check that HTF fill valve (#3)
is closed and locked with the
locking pin.
NOTICE:
The HTF fill valve must
remain closed and locked during
normal operation. An open HTF fill
valve will cause HTF leakage.
wc_gr008057
b
a
wc_gr007784
#3

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Wacker Neuson E 2200 and is the answer not in the manual?

Wacker Neuson E 2200 Specifications

General IconGeneral
BrandWacker Neuson
ModelE 2200
CategoryHeater
LanguageEnglish

Related product manuals