9 Operation and use
22 100_0202_op_0017.fm
9 Operation and use
9.1 Initial operation
9.1.1 WP
The supplied control handle needs to be attached prior to initial operation.
1. Align the control handle on the provided bores.
2. Tighten the control handle on the left and right with the screws. The torque setting is 86 Nm.
9.1.2 VP
The machine is delivered fully assembled and is ready for operation out of the box.
9.2 Before commissioning
9.2.1 Inspection before commissioning
Check the machine and components for damage. In the event of visible damage, do not operate the
machine and immediately contact Wacker Neuson service.
Ensure that loose packaging material has been removed from the machine.
Check the fuel level.
Check the engine oil level.
Check the fuel lines for leak tightness.
Check to ensure the screwed connections are firmly seated.
9.3 Notes about operation
WARNING
Improper handling may result in injury or serious material damage.
Please read and follow all safety instructions in this operator's manual.
Item Designation
1 Control handle
NOTICE
Perform control procedures according to the Maintenance chapter. If necessary, top off
missing fuel, lubricants and coolants, see chapterTechnical Data.
WARNING
Danger of tipping
There is a serious risk of injury from slipping or tipping over of the machine.
Near edges, at least 2/3 of the machine must be on a load-bearing surface.
Turn off the machine and lift it back onto a load-bearing surface.