29 / 47
For more detailed information, please ask representative of WATTUNEED to get a copy of passive mode
communication protocol.
PV input mode selection: WKS Iinverter has 2 MPPT channels. The 2 MPPT can operate independently, also can
operate in parallel. If the PV strings are connected in parallel outside the inverter, you should choose the “in parallel
mode”, otherwise use the default setting (independent mode).
5. Set EPS Mode
1.EPS Mode Control
1.Enable EPS Mode
2.Disable EPS Mode
2.Set EPS Changeover Time
(
default 20ms
)
***S()
If PV generation > LOAD consumption (ΔP > 100W),
WKS I inverter will charge battery.
If PV generation = LOAD consumption, WKS I
inverter wont’ charge or discharge battery.
If PV generation < LOAD consumption (
Δ
P
>
100W), WKS I inverter will discharge battery.
4) If PV generation is normal,but LOAD consumption=0,
the surplus power will be stored in the battery.