Commissioning steps Testvaluesorconrmation
1.) Serial number on the type plate
_______________________________________
2.) Electrical wiring / connection / fuse protection checked in
accordance with technical data of installation instructions and
VDE regulations?
2.) System ushed?
3.) System lled and water treatment carried out?
- pH value set
- total hardness set
________________ pH value
____________________ °dH
4.) Appliance and system vented?
5.) System pressure 2.0 - 2.5 bar?
6.) Water connections checked for leaks?
7.) Trap lled?
8.) Gas restrictor inserted according to gas type? Natural gas
LPG
Wobbe index _____________ kWh/m³
Net caloric value, heating ______ kWh/m³
9.) Gas supply pressure checked?
10.) Gas tightness test carried out?
11.) Switch boiler ON, set control unit to OFF / Standby.
12.) Standard setting of control unit set?
27. Commissioning report