XCell
TM
ATF System with C410:V3 Controller
An approved lubricant may be used to facilitate coupling of parts containing an “O” ring
seal.
10.4 Controller Maintenance
Bi-annual Maintenance
1 P2 verification or calibration
2 Complete system visual inspection for damage or risk to the operator or surrounding
personnel
3 P-box vacuum system leak test
4 Verification that the pressure regulator is set to correct pressure
5 Inspection of air and vacuum connection to the P-box
6 Inspection of pneumatic fittings
7 Inspection of the pneumatic tube from the P-box to the XCell™ ATF pump housing
8 Inspection of enclosure for damage, locks and hinge performance, external electrical
connection, cables and pneumatic tubing
9 PRV verification or calibration
10 PRV trend verification or calibration
11 PV verification or adjustment
12 Inspection that all components inside the enclosures are secured and intact
13 P2 verification or calibration
14 Inspection of touch screen alignment and performance
15 Flow test (low, middle and high flow rate)
Every Four Years
16 Replacement of complete pneumatic manifolds and pneumatic tubing
17 Annual maintenance routine