23VCCX2 Controller Technical Guide
START-UP AND COMMISSIONING
Powering Up and Conguration
Before Applying Power
In order to have a trouble free start-up, it is important to follow a
few simple procedures. Before applying power for the rst time, it
is very important to run through a few simple checks.
Power Wiring
One of the most important checks to make before powering up the
system for the rst time is to conrm proper voltage and transformer
sizing for each controller. Each VCCX2 Controller requires 15 VA
of power delivered to it at 24 VAC. Use separate transformers for
each device (preferred) or power several devices from a common
transformer.
WARNING: Observe polarity! All boards must be wired
with GND-to-GND and 24 VAC-to-24 VAC.
Failure to observe polarity will result in
damage to one or more of the boards.
Check all wiring leads at the terminal block for tightness. Be sure
that wire strands do not stick out and touch adjacent terminals.
Conrm all sensors required for the system are mounted in the
appropriate location and wired into the correct terminals on the
VCCX2 Controller.
After all the above wiring checks are complete, apply power to the
VCCX2 Controller.
Conguring the Controller
The next step is conguring the controller for specic requirements.
In order to congure the VCCX2 Controller, use an operator
interface. Four different operator interfaces are available for
programming and monitoring of the VCCX2 Controller. See Figure
13, this page. They are as follows:
• Modular Service Tool SD
• Modular System Manager SD
• PC with Prism 2 Software installed and CommLink 5
• System Manager TS-L (Touch Screen - Limited Access)
Any of these devices or a combination of them can be used to
access the status, conguration, and setpoints of any controller on
the communications loop.
NOTE: Use Prism II to configure units with RSMD-A,
RSMVHPQ and RSMZ modules.
If using the Modular Service Tool SD or the Modular System
Manager SD for programming, refer to the VCCX2 Controller
Operator Interface SD Technical Guide. If using a computer and the
Prism 2 software for programming, refer to the Prism 2 Technical
Guide.
If using the System Manager TS-L for monitoring, please see the
System Manager TS-L Technical Guide.
No matter which operator interface is used, AAON recommends
proceeding with the programming and setup of the VCCX2
Controller in the order that follows:
Congure the controller for the application.
1. Program the controller setpoints.
2. Program the controller operation schedules.
3. Set the controller current time and date.
4. Review the controller status screens to verify system
operation and correct controller conguration.
NOTE: For BACnet Conguration, see Appendix C.
Figure 13: Operator Interfaces
STATUS
SETPOINTS
SCHEDULES
OVERRIDES
ALARMS
7
8
0
DEC
MINUS
9
4 5
6
1
2 3
ENTER
ESC
CLLAR
DOWN
UP
PREV
NEXT