ACS 6000 Commissioning Manual
3BHS135824 ZAB E01Rev. D 23 (of 62)
All electrical instruments as well as pumps and electrically controlled
valves are shown in the circuit diagram of the motor auxiliaries.
Operation of these devices will be checked when the external
signals of the drive are tested, see Chapter 8 - Checking I/O, 8.3.1
Motor Signals.
Quality and flow rate of the cooling water.
Visual check of the instrumentation.
Instruments and cooling fans are shown in the circuit diagram of the
motor auxiliaries. Operation of these devices will be checked when
the external signals of the drive are tested, see Chapter 8 -
Checking I/O, 8.3.1 Motor Signals.
Leakage
During the first operating hours of the water cooling system, it must
be checked that the cooling system of the motor does not leak.
Connection of space and oil heaters.
Follow the checkpoints of the commissioning report.