ACS 6000 Commissioning Manual
3BHS135824 ZAB E01Rev. D 61 (of 62)
Chapter 14 - Finishing the Commissioning
14.1 Spare Parts
Check that the spare parts are available at site and are according to
ordered scope of supply. If they have not been ordered, make a remark
in the commissioning report.
If there is a spare AMC board, the final version of the FLASH circuit
must be copied on it.
14.2 Customer Training
Instruct the customer’s operators how to use the drive. Explain different
control modes (local/remote) if applicable.
If customer has not been trained by ABB, explain that the customer has
the possibility to participate ABB training programs in training centers
worldwide.
14.3 Parameter Back-up
Read all the parameters from the drive by using DrivesWindow program
and save them into a file. Be sure that all parameter groups are open
and that all parameter values are saved properly. In DrivesWindow use
the option “open all groups”.
Hand out a copy of the parameter settings to the customer or, if
available, save parameter files on the PC of the customer.
14.4 Customer’s Signature
After the test runs have been performed and the commissioning report
has been filled in properly, print out the report and ask the customer for
acceptance. This will initiate the warranty period.
The commissioning report must be sent to the MV AC Supportline (for
address see 14.6 Documents and Back-up Copies), preferably in
electrical format. Thus, fill in information about customer’s
representative who signed the report; ie. name, date and place and
where the original document with the signature is stored.