21
Fault Tracing Thyristors
3ADW000488R0101 DCS880 Service manual e a
Ripple monitor
If the ripple monitor fault occurred, a fault tracing as described above must be carried out:
Check the fuses and the thyristors, according to the statements before.
If the power section seems to be ok, but still one or more thyristors don’t take current, something went
wrong in between the firing pulse generation and the thyristor’s gate; in this case check:
Is a firing pulse present on the primary side of the firing pulse transformer?
Is a firing pulse present on the secondary side of the firing pulse transformer?
Is the firing pulse transferred to the gate of the thyristor (loose gate connector)? Are all electrical
connections still healthy?
Can the thyristor be fired with the applied firing pulse? Is the pulse form of the firing pulse identical at
all measuring positions?
Check the settings of the current controller.
Check the AC mains network by taking recordings of the line voltage and current at all 3 phases at the same
time.