5. Commissioning
The enabling device should only be commissioned by specialist personnel who have been trained to work
with the machine.
It is always important to make sure that the operation of the device is not tampered with and ensure the
intended use (see scope of application) is complied with.
Attention!
Other protective measures must be taken in order to protect other people in the same or adjacent
hazardous area.
Functional Test
At first commissioning after installation, a functional test based on the application case must be carried out
in accordance with current guidelines for the case of application and the relevant harmonized standards.