4.1 Condition on delivery
The factory assembled panels are dispatched
without I
s
-limiter
TM
inserts (Inserts are packed
separately in separate special packing).
The panels are checked at the works for:
- completeness of the equipment installed
- with reference to the terms on customer order
- Prior to dispatch, panels are subjected to
routine tests
4.2 Packaging
The I
s
-limiter
TM
panels are packed for transport in
following types:
• Panels with seaworthy packaging or similar
(including packaging for containerized
shipments):
- Sealed in polythene sheeting
- Transport drying agent bags included
- Moisture indicator included
- When aluminum composite sheeting is
used, a sight window is fitted for checking
• Observe the directions for use of the drying
agent bags
The following applies:
- Colored indicator blue: contents dry
- Colored indicator pink: contents moist
(relative humidity above 40%)
4.3 Transport
Figure 4.1-4.4
Normally, each individual panel is a separate
transport unit. The panels are fixed on wooden
pallet with bolts. The foundation frame for
installation at site is packed separately during
dispatch of panel for transport to customer site.
Following precautions must be taken during
transport of the panels:
- Transport switchgears upright
- Take the high center of gravity into account
- Carry out loading operations only after
ensuring that all precautionary measures to
protect personnel and materials are taken
- Use crane, fork-lift truck and / or manual
trolley jack
When performing loading work, take all necessary
precautions to avoid injury and damage to the
materials.
Loading must only be carried out with
• crane
• forklift and/or
• Trolley jack
Handling by crane:
• Use lifting ropes of appropriate load capacity
with spring catches with eyebolt diameter of
30 mm
• Maintain a rope angle of 60° from the
horizontal between the shackles and crane
hook
• Hang the switchgear using all lifting hooks!
—
4. Dispatch and storage