Mechanical and Electrical Installation
C220/C420 Mechanical and Electrical Installation
32
1) Install the inverter vertically so that the heat may be expelled from the top.
However, the equipment cannot be installed upside down. If there are multiple
inverters in the cabinet, parallel installation is better. In the applications where
up-down installation is required, please install the thermal insulating guide plate
referring to the schematic diagrams for standalone installation and up-down
installation.
2) The mounting space shall be as indicated as the above diagrams, so as to ensure
the heat sinking space of the inverter. However, the heat sinking of other devices in
the cabinet shall also be considered.
3) The installation bracket must be made of flame retardant materials.
4) In the applications where there are metal powders, it is recommended to install
the radiator outside the cabinet. In this case, the space inside the sealed cabinet shall
be large as much as possible.
3.1.3 Under cover remove and installation
Fig.3-2 Plastic shell demolition plans