Work commencement
34
AMALOG BAH0017.1 11.08
8 Work commencement
1. Place machine in starting position (standstill).
2. Lower the correct track marker (see seed drill operating manual).
Switch through the track markers if the correct track marker is not lo-
wered.
The tramline control is coupled with the track marker control.
3. Press
key.
→ Setting the tramline counter [e.g.: tramline counter 4, see (Fig. 8,
on page 17) under "START" heading].
Display during standstill:
Figure 1 (Fig. 30
1) indicates the travel
speed (km/h).
Figure 2 (Fig. 30/2) indicates the tram-
line counter 4 an.
Fig. 30
4. Press and hold
key.
5. Press
key.
→ The part area counter goes to 0 [ha].
6. Start.