4 Transport / Commissioning
BNNbOO
ID: 1138310 Issue date January 01, 2010
36
Commissioning
The machine as delivered is essentially ready for operation. Observe the
following before commissioning:
Familiarize yourself with the manual.
Perform ten-operating-hours maintenance. This procedure is described in
the "Maintenance" section.
Make sure that the joint protection is open.
Roller with pneumatic wheel (combined roller)
If using a combined roller, you must check tire pressure and adjust as
required. The ex works pressure is set to 2.5 bar.
Tire pressure must be adjusted to suit the compaction condition of the
ground:
Tire pressure too low Tire pressure OK Tire pressure too high
NOTE
The tires must be replaced if the fabric is visible on the tire surface.