Adjust engine inlet and outlet valves (2) x
Check fuel injectors (2) x
Inspect starter motor xx
Inspect turbocharger xx
Inspect waterpump xx
Inspect charging alternator xx
Inspection by Atlas Copco service technician x x x
Generators in standby application have to be tested on a regular basis. At least once a
month the engine should run for one hour. If possible a high load (> 30%) should be
applied so that the engine reaches its operating temperature.
Maintenance schedule Daily
50 hrs
after initial
start-up
Every 500
hours
Every 1000
hours
Every 2000
hours
Yearly
Service pak - - 2912 4505 04 2912 4506 05 2912 4507 06 -