17
4. Route the Cable through the Top Trough Safety Cable
Pulley(s) and across the lift. (See Fig. 9.5)
5. Route the Cable the same way on the Powerside
going back down the post.
6. Route the Cable over the Top Pin on the Safety
Handle. Insert the Cable end through the hole on the
threaded post. (See Fig. 9.6)
7. Pull the slack out the Safety Cable and hold tension
as the Cable is being tightened. Tighten jam nuts on
either side of the Cable to secure it into place.
(See Fig. 9.6)
STEP 10
( Installing Hydraulic Lines)
1. Install the Bulkhead Tee fitting into the Powerside
Column. The through hole is located approximately 90
inches from the floor on the back wall of the Powerside
Column.
2. Connect the Powerside Cylinder Hose to the Tee
Fitting Be sure to route the hose through the Retainer
Rings inside the columns.
3. Route the Offside Cylinder Hose (Crossover Hose) up
through the Offside Post and across the Top Trough, down
the Powerside Column and connect it to the Bulkhead Tee
Fitting. (See Fig. 10.1)
NOTE:
Do not use Teflon Tape or any type of
sealant on JIC type Hydraulic Fittings.
NOTE:
Make sure to tighten both nuts equally so as to
keep the Safety Cable centered
Fig 9.5
Fig. 9.6
Fig. 10.1