XPR-9 Series Two-Post Lifts
24
P/N 5900371 — Rev. D2 — May 2023
18. On both Lift Posts, locate the two Double Threaded Rods (M10 x 275 mm rods, threaded on both
ends), two Nuts, and two Washers in the Parts Box, put them into place through the top of each
Post (they go all the way through the top of the Post), and tighten them in place on both ends.
Refer to the figure on the next page.
Install the Cylinder Chain and Roller
The Lift Cylinder drives a Chain connected between the Base plate and the Lift Head.
To install the Cylinder Chain:
1. Perform these operations while the Posts are on their side with the interior accessible and the Lift
Head free to move.
2. Retrieve the Chain with its Master Links.
XPR-9TF Chain (5210251)
XPR-9SBT Chain (5210116)
3. On XPR-9SBT only, verify the Cylinder Leveling Plug is in Place. Refer to the figure below.