Commissioning 39/56
RE 93223-01-B/09.2020, A21VG Series 10, Bosch Rexroth Corporation
8 Commissioning
WARNING
Danger while working in the danger zone of a machine/system!
Danger to life, risk of injury or serious injuries!
▶ Pay attention to and rectify potential danger sources before operating the axial
piston unit.
▶ Nobody may stand in the danger zone of the machine/system.
▶ The emergency stop button for the machine/system must be within the
operator’s reach.
▶ Always follow the instructions of the machine/system manufacturer during
commissioning.
CAUTION
Commissioning of an incorrectly installed product!
Risk of injury and damage to equipment!
▶ Make sure that all electrical and hydraulic ports are connected or plugged.
▶ Only commission a completely installed fault-free product with original
accessories from Bosch Rexroth.
8.1 Initial commissioning
During all work for commissioning the axial piston unit, observe the general
safety instructions and intended use detailed in chapter 2 “Safety instructions”
on page8.
▶ Connect the gauge for the operating pressure, case pressure and suction
pressure to the specied measuring points on the axial piston unit or in the
hydraulic system, to check the technical data at rst operation.
▶ During the commissioning process, monitor the temperature of the hydraulic
uid in the reservoir to ensure that it lies within the permissible viscosity limits.
8.1.1 Filling the axial piston unit
Professional lling and air bleeding is necessary to prevent damage to the axial
piston unit and to maintain correct function.
Usually, thecleanliness level ofcommercial hydraulic uids isinsufcient for
our components. These hydraulic uids must beltered during lling using
anappropriate lter system tominimize solid particle contamination and water
inthe system.
Use only ahydraulic uid that corresponds tothe following requirements:
You can nd details on the minimum requirements for hydraulic uids in
BoschRexroth data sheets 90220, 90221, 90222, and 90223. The titles