Boiler installation 7
13
We reserve the right to make any changes due to technical modifications.
Installation and maintenance instructions Logano G334 X gas-fired boiler • Issue 09/2005
7.3 Installing the side panels and the front boiler jacket
z Press insulation panels into the side between the
cast feet.
z Insert thermal insulation mats for the right side panel
behind the gas connection pipe.
z Fasten the two side panels with two self-tapping
screws at the bottom and one at the back of the boiler
z Position the intermediate panel thermal insulation
mats on the top of the front of the boiler with the fabric
side on the outside.
z If the two side hooks on the front boiler jacket are not
in position, bend them with pliers and push them into
the slots in the side panel edges from behind.
z Fasten the two rear tabs on the front boiler jacket to
the side panels with two self-tapping screws.
Fig. 7 Insulation panels
1 Insulation panel
1
Fig. 8 Side panels and front boiler jacket
1 Rear tab
2 Side hook
3 Side panel screws
3
1
2