6. PREVENTIVE MAINTENANCE
For the BME:
Switch off the machine.
Open the upper cover and the doors.
Daily maintenance
Remove the metal parts (stitches) from clinchers by pushing on the handle 3 times. If you 1.
do not do it there is a risk of poor stitching or jam.
Empty the waste bin. If you do not do there is a risk of machine stop with the error 2.
message “waste bin full”. Lift up to pull the bin.
Note: it is possible to empty the waste bin during the running of the machine.
The machine will stop if the bin is not back after 50 cycles