MAN.234 Rev.6 ENG - Use and maintenance manual S19HD page 102 of 126
11 Stability and over-
load tests
During the commissioning of the ma-
chine, in the final test, we carried out the
following stability and overload tests to
verify S19HD structural strength.
These tests shall be carried out only on the
first test of the machine. You shall not repeat
tests with the same loads.
NOTES.
NL: nominal load.
TL: test load.
Stability tests
Test
nr.
Load
(Kg)
Aerial part position
Side
Out-
come
Out-
reach
(m)
Panto-
graph
Boom
1
220 (NL)
+
130 (TL)
7,60
com-
pletely
lifted
hori-
zontal
lateral
(at
1.5°)
OK
2
80 (NL)
+
60 (TL)
10,40
com-
pletely
lifted
hori-
zontal
lateral
(at
1.5°)
OK
Overload tests
Test
nr.
Load
(Kg)
Aerial part position
Side
Out-
come
Out-
reach
(m)
Panto-
graph
Boom
1
220 (NL)
+
110 (TL)
7,60
com-
pletely
lifted
hori-
zontal
lateral
OK
2
80 (NL)
+
40 (TL)
10,40
com-
pletely
lifted
hori-
zontal
lateral
OK