Chapter 4 – Setup & Configuration
4.1 User Checklist
Follow this checklist to configure the CL1/CL2 for first time operation or after a software upgrade.
___ Set passwords (section 5.6.3)
___ Set system date and time (section 5.5.7)
___ Gas selection (section 5.5.9)
Appendix E contains the specifications for each gas.
___ Alarm level settings (section 5.4.5)
___ Latching relays (section 5.5.3)
___ Energized Relays (section 5.5.5)
___ Idle Timeout (section 5.5.6)
___ Testing Contacts (section 5.4.7)
___ Adjustment of 4-20 ma (section 5.5.8)
___ Install new ChemLogic tape (section 6.3)
___ Install removable media (section 6.6)
___ Format removable media (Appendix F.3)
___ Tape Saver Mode (TSM section 5.5.)
___ Grease the Gate Cam (section 6.7)
___ Verify Sample Inlet flow ( post software upgrade only )
Setup complete - Ready for monitoring.