SECTION 13 SUPERSTRUCTURE
Page 8
TD-25M EXTRA DRESSTA
NOTE: Sequence of cab to platform securing bolts torquing described in points 1and 2 is to be
followed strictly. Any change in torquing procedure may lead to cab stress and deformation.
3. Reconnect A/C system quick couplings (2, Fig. 13.1), install the couplings cover.
4. Thread wipers hoses down thru hole in the platform and reconnect hoses to the wipers washer
tanks (1, Fig. 13.4).
5. Reconnect cab head lamps wire harness plug (4, Fig. 13.2) and ROPS lamps plug (6).
6. Reconnect heater control potentiometer wire harness plug (3) and A/C heater switch wire
harness plug (5).
7. Reconnect electrical connectors for two cables (1 and 2), supply (+) and ground (-) of the cab
electrical system.
8. Install left, right and rear plastic shields in the cab. Install the armrest.
9. Position ROPS structure. Install the bolts (1, Fig. 13.1) securing ROPS to the crossbeam
assembly (five bolts on each side) and torque them to 1500 [Nm].
10. Turn electrical master switch to „ON” position. Start the engine. Refer to Operator’s Manual.
Check for leaks disconnected previously hydraulic lines of drive train control valve
(1, Fig. 13.5) pilot lock valve (4) and switching valve (7). Stop the engine.
11. Install console cover plate and transmission pressure filters cover.
12. Install floor plate (2, Fig. 13.6) in the cab.