3.3 Hanging the Equipment
3.3.1. Pump Cabinet Installation
1. Position the wall mounting bracket against the wall at eye level.
On sheetrock walls, align the center
mounting hole to a wall stud. Wall Moun
ting bracket MUST BE securely anchored to the wall. Proper
wall anchors or toggle bolts should be used.
2. Using a pencil, outline each of the holes in the offset mounting wall bracket.
3. Drill the outlined hole with a 1/4-inch masonry bit and place a wall anchor (supplied in the installation
kit) into each hole.
4. Secure the
wall bracket to the wall using
the supplied wall anchors.
Be careful when lifting the Pump Cabinet. It weighs 27 kg. If you must lift it by yourself, hold it close to your body.
On sheetrocked walls, align mounting holes with wall studs wherever possible.
5. Lift the Pump Cabinet up
and onto the mounting bracket, utilizing the mating bracket on the
back
of the
cabinet.
6.
With the Pump Cabinet on the wall, use a pencil to outline the center hole on the bottom flange.
7.
Remove the Pump Cabinet from the wall.
8. Drill the outlined hole with a 1/4-inch masonry bit and place a wall anchor (supplied in the installation
kit) into the hole.
9. Lift the Pump Cabinet back up and onto the mounting bracket.
10.
Secure the bottom flange of the Pump Cabinet to the wall using the wall anchor.
Backflow prevention to b e installed as close as possible to the Dispenser
Plastic Wall
Anchor
Mating Bracket on back of Pump Cabinet
Pump
Cabinet
Wall Mounting
Bracket
Center of Bottom Flange
Screw