3 Installation
3.1 Basic requirements
During the operation of the energy storage system, the temperature of the air outlet on the
left side of the cabinet may be relatively high. Please do not install it in a location where it
is easy to access.
Do not install in areas where flammable and explosive materials are stored.
Do not install in a location that children can touch.
The energy storage system is installed on the ground and fixed with wall-mounted
components.
The energy storage system cannot be installed to tilt it forward, place it upside down, tilt
backward and tilt sideways.
3.2 Choose position
Please select solid brick concrete structure, concrete wall and floor for installation location. If
other types of wall and floor are selected, wall and floor must be made of flame-retardant
materials and meet the requirements for equipment fixation.
The Additional Cabinet is delivered with the Emaldo Power Core and serves as an intermediate
device connecting the energy storage system to the primary distribution box. AC input & output
and energy metering communication lines of the system are connected to the Additional
Cabinet, and then connected to users' existing primary distribution box before distributing
electric power.
A portion of user load can also be obtained by adding new circuit breakers to the reserved rails
in the Additional Cabinet.
Because the Additional Cabinet is closely related to the energy storage system, it shall be
placed in a relatively suitable location to connect the Emaldo Power Core and users' existing
primary distribution box, so as to distribute electric power reasonably.