Levelflex M FMP40 FOUNDATION Fieldbus Mounting
Endress+Hauser 11
Supporting probes against warping
For WHG approval:
For probe lengths 3 m a support is required (see figur).
For GL/ABS approval:
Rof probes 16 mm 1 m permissible, rod probes 6 mm not permissible.
L00-FMP4xxxx-17-00-00-en-055
2.3.6 Special notes for bulk solids
Ø <26 mm
#
#
Ø 17...18 mm
Probe rod
Short metal pipe
e.g. welded in place
approx. 50 mm
Sleeve bored tight
to ensure electrical
contact between the rod
and sleeve!
Ground the probe
when welding the
sleeve!
In the case of bulk solids, as great a
distance as possible from the fillling
curtain is especially important to avoid
wear.
In concrete silos, a large distance (B)
should be observed between the probe
and the concrete wall, if possibile 1 m,
but at least 0.5 m.
The installation of rope probes must be
carried out of carefully. If possible,
installation should be carried out when
the silo is empty.
Check the probe regularly for defect.