6 Commissioning
Make sure that all post-connection checks have been carried out before you commission your
device:
• See Section ’Post-installation check’, → ä 14
• Checklist Section ’Post-connection check’, → ä 21
After the operating voltage is applied, the display and the green LED are illuminated. The device
is now ready to operate and can be configured via the keys or the "FieldCare Device Setup"
parameter configuration software (→ ä 24).
!
Note!
Remove the protective foil from the display, as otherwise legibility is impaired.
Expert menu The Expert menu offers access to all operating options of the device, including fine
tuning and service functions.
• Jump directly to parameters via Direct Access (only on the device)
• Service code for displaying service parameters (via PC operating software only)
• System (settings)
•Inputs
•Outputs
• Application
•Diagnostics