19Installation instructions
EN
Additional installation materials
Material Description of use
Screws For hanging the rear attachment
bracket and ventilation unit on
the wall (if applicable). Select
the screws according to the wall
material.
Sheet metal screws For attaching the rear attachment
bracket onto the ventilation unit.
Wall mounting box For installing eWind operating
panel.
Cables As specied in chapter "Preparing
for electrical installations" on
page 17.
Duct tape For sealing.
Insulation sheets (soft foamed
plastic)
For preventing structure-borne
noise.
Insulation material (foamed
plastic and/ or wool,
depending on where the unit
will be installed)
For retaining heat and coolness.
Rivets For attaching the ventilation
ducts onto the unit.
Spirit level For making sure that the unit is
level.
Water pipe For connecting duct coils and for
disposing of condensate water.
Water trap For condensate water drain.
Reducing ttings for duct
connections
For tting the ducts in the
ventilation system. NOTE: Always
use reducing ttings, if necessary.
Dampers To keep cold air out.
Silencers To reduce possible noise.
Suitable grommets for duct
mounted sensors
For mounting sensors in the
ducts.
Shut-o valves To facilitate servicing of unit.
Hydronic balancing valves To properly adjust the water ow.
The order of Freeway connector’s pins is marked on the
controller card.
Modbus registers are available on Enervent webpage
www.enervent.
CAUTION
CAUTION: Do not connect the external bus to
the motherboard before the bus is programmed
and compatible with the unit control.
INSTALLATION
NOTE: Before you install the ventilation unit,
make sure that there are no foreign objects in
the ventilation unit and duct system.
• Refer to the model-specic dimensional drawings
in the back of this manual for your specic
ventilation unit type.
• Inspect the order of duct connections to avoid
cross connections.
• Do not start the ventilation unit when it is installed
until the building is taken into use.
• If the ventilation unit is started too early, the
ventilation system can be contaminated by
building dust.
• Make sure that the ventilation unit duct
connections are the same size as the duct.
• Use a circular duct tting to connect the unit
to the duct.
• Insulate the duct all the way to the unit casing.