IQ System Controller 3/3G Quick Install Guide
Control (CTRL) wiring
between system components
Section C - Wiring
Control wiring guidance for the Enphase Energy System:
Refer to the following wiring sequences to understand the position
of the header with termination resistor, wiring order, and drain wire
termination location.
NOTE: Ensure the following guidelines are followed to avoid
failures during system commissioning:
One header with termination resistor should be installed
on each component that is at the extreme end of the
control network.
NOTE: Total length of CTRL wiring across the system cannot
exceed 250 feet to ensure the system operates as per
specications.
The drain wire should only be terminated on one end of the
control wiring between system components
It is recommended that the drain wire be terminated at the
component from which the control wiring for the section is
initiated
The same conduits can be used for power and control wire
routing only when using an Enphase CTRL cable i.e.,
CTRL-SC3-NA-01.
The following are four common wiring sequences:
Sequence 1a: IQ Combiner 5/5C → IQ System Controller 3G → IQ Battery(s) 5P

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the enphase IQ System Controller 3 and is the answer not in the manual?

enphase IQ System Controller 3 Specifications

General IconGeneral
Brandenphase
ModelIQ System Controller 3
CategoryController
LanguageEnglish

Related product manuals