2.1 Precautions for installation
When handling the unit, you must keep the unit vertical. It is prohibited to handle the unit
horizontally or upside down. Any damage caused to the unit for failing to observe this instruction
shall not be covered by the warranty.
Before installing the equipment, you should decide how to modify the building to facilitate the
piping, cabling and duct construction. Please install the units strictly according to the relevant
drawings. For the reserved installation and maintenance space, please refer to the engineering
dimension drawing provided by the manufacturer.
Indoor unit must be installed vertically,outdoor condenser should be installed in the well-ventilated
area.
2.1.1 Storage and operation environment requirements of XRow
series row air conditioner
For the storage and operation environment requirements of the XRow series air conditioner, please
refer to Table 2-1 and Table 2-2.
Table 2-1 Storage environment requirement
Indoor, clean, dust free, etc
The total transportation and storage time shall not exceed 6 months; otherwise, the performance