6 Daily Use
6.1 Starting-up and running
Installation section must be carried out before this chapter can be performed.
When the main switch is pressed, an initial procedure starts and secure that the machine is ready for
production. The POWER ON light will turn on when the machine is ready.
6.2 Adjustments
Before starting up and running, the machine must be set up to the correct bottle size.
6.2.1 Adjusting the round table inner bottle rail
Adjust the inner bottle rail by loosening the
bolts and move the rail in or out; depending on
bottle size. The bottles should be stopped by
the rail in such a way that only one bottle at a
time can pass the space between the inner and
outer rail.
6.2.2 Adjusting the bottle sluice
The sluice consists of two guides.
• An adjustable guide (2) which can be adjusted for bottle size.
• A safety guide (4) which can’t be adjusted but can be moved along the yellow arrow in order to
prevent fingers from being damaged.
• Loosen the fastening screw.
• Move the guide (2) in. (downwards in picture)
• Place a bottle in each end of the sluice (3).
• Move the (2) out until there is about 1mm of room on each side of the bottle.
• Fasten the Screw (1)