3.2 Filling the pellet store
CAUTION
Filling the store when the boiler is switched on
could result in damage and consequential injury!
When filling the fuel store:
❒ Switch off the boiler by tapping “Boiler OFF”
➥ The boiler follows the shutdown procedure and switches to "Boiler off"
status
❒ Allow the boiler to cool for at least half an hour
When the boiler has cooled down:
❒
Before filling check the store for fines and clean if necessary
➥ Observe the general advice for working in the store.
⇨ See "General advice for working in the store" [page 22]
❒ Close all openings to the store to seal out dust
❒ Fill the store with pellets
➥ Only use permitted pellets
⇨ See "Permitted fuels" [page 11]
3.2.1 General advice for working in the store
Risk of injury due to moveable parts!
Shut off the feeder unit before entering the store!
When cleaning the store an increased amount of dust may be
generated. Wear a dust mask when working in the store.
Adequately ventilate the store before entering. Keep the door open
and always have a second person present. Observe the CO
concentration limit (< 30ppm).
Slick surfaces in the fuel store present a slipping hazard!
3
Operating the System
Filling the pellet store
22 Froling GesmbH | A-4710 Grieskirchen, Industriestraße 12 | www.froeling.com