The startup test can take anything from just a few seconds up to several minutes de-
pending on national regulations. The time elapsed is indicated by a bar shrinking from
the top down.
Whenever two scale divisions stop flashing and disappear, 1/10 of the total duration
of the test is over.
Operation of
Feeding Energy
into the Grid
- Once the tests have been completed, the inverter starts feeding power into the grid.
- The display shows the present power feeding into the grid.
- The Operating Status LED lights up green, and the inverter starts operating.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Fronius IG Plus 100 V-1 and is the answer not in the manual?

Fronius IG Plus 100 V-1 Specifications

General IconGeneral
BrandFronius
ModelIG Plus 100 V-1
CategoryInverter
LanguageEnglish

Related product manuals