RX900 S2 Operating Manual 65
Hardware installation
Ê Fit the PRIMECENTER/DataCenter rack cable management as described in
the Technical manual for the corresponding rack.
Preparing the server
Figure 9: Preparing the server
Ê Place the inner parts of the rails on the sides of the server and secure them
with four screws.
I Please note that the same type of rail is installed on the left and the right
side of the server. Therefore, the locking lever is released as follows:
– Left side oft the server: Push upward
– Right side of the server: Push downward