28 1200C-2000C Fire Alarm Control Panel, Repeater, and Black Box Installation Manual
Commissioning networks
Once the control panel has been commissioned correctly, the following steps are
required to initialize and configure a network.
1. Configure the network setup (via the Setup menu or using a PC)
2. Investigate and fix all faults that are reported
3. Check the status of the systems on the ARCNET network that are configured to
communicate with the repeater. Faults regarding communication with repeater
node identification address should disappear when the ARCNET network is
operational
4. Check all connections to panels by emulating them
5. Check panel fault reporting by switching off each panel one by one and checking
that the missing panel is reported by the other panels in the network
6. Check fire and fault reporting
7. Check all that all network input and output devices are working correctly
8. Reset all repeaters and control panels

Other manuals for GE Security 1200C

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE Security 1200C and is the answer not in the manual?

GE Security 1200C Specifications

General IconGeneral
BrandGE Security
Model1200C
CategoryControl Panel
LanguageEnglish

Related product manuals