2.1 INSTALLATION OVERVIEW
This section provides instructions for receiving, unpacking, and placement of the
TotalPlant Solution (TPS) System LCN equipment cabinets, Operator Interface Stations
(OIS) and Universal Stations (USs), see Figure 2-1. The instructions assume that all of the
system LCN modules and all interconnecting LCN cables within the cabinets and consoles
have been installed and connected at the factory as shown in Figure 2-2.
1253
Figure 2-1 —TPS Universal Station and Equipment Cabinet